Is there a way to see the epic burn down with items completed vs utilizing story points to calculate this? 

1 answer

1 vote
Staffan Redelius
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 27, 2025

Hi @Jessica Sullivan  and welcome to the community.

If I understand your question correctly you just want to see the Epic burndown based on completed work items?

Unfortunately this is not possible, i think the main reason is that the prediction would be to coarse and not give a proper indication in resolution time for the Epic.

If you have only 10% estimated issues in the Epic the Epic will be based on the estimated issues even if your teams capacity is in fact much larger.

I hope this helps even if it wasn't the answer you were looking for.

Best regards,
/Staffan 