I have an issue, it needs to be approved by 11a by a specific group (group 1). then it moves forward and needs to be approved by a 2nd group by 2p, then a 3rd group by 4p.
what validation script can I use so at 11:01a, it can no longer be approved by group 1, nor move forward for that day? but anytime before 11a the next day it can be approved.
Ditto for the 2:01p approval time by group 2 and ditto for the 4:01p deadline for group 3.