can we show story points of two linked tasks in a single issue type?

Durga prasad panda
Contributor
July 8, 2019

Hi 

WE have 2 issues types. We link them to use it as an EPIC type.
Suppose we have two issue type A-Task and A-Sub-task.

We have linked them . Is there a possibility to see all the storypoints of A sub-task types that are associated with an A-task.

1 answer

0 votes
Jack Brickey
Community Champion
July 8, 2019

No you can’t do that. While you can have a task sum up the estimations of sub-tasks, linking does not provide the same feature. You could consider an addon and scripting. 