Using Jira Agile (free plan) with scrum, how do I change the scheduled workdays for a project? When I look at my sprint it indicates I only have 4 days left but I don't. I'm working 7 days per week and would like it to indicate such.
How do I change that?
The "workday" setting is at the Board level, not the Project level.
From your Scrum Board or Kanban Board go to "Board Settings" (in the 3-dots menu) and then "Working Days".
Adjust that and see if it fixes things.
I also have found the "number of days remaining in a sprint" to be wrong at times. I've never quite understood why. I did a quick scan and didn't find anything in the JAC.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Here's a suggestion about some other behaviors for that days count field: https://jira.atlassian.com/browse/JSWCLOUD-21581
Kind regards,
Bill
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks @Bill Sheboy for the link to that JAC issue - voted, watching and commented!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.