eazyBI for next sprint

Kristin Lyons
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 20, 2022

Is it possible to create an eazyBI report for the immediate next sprint?  We want to be able to easily tell how many hours we have estimated without having to update the report repeatedly to update the Sprint.

1 answer

1 accepted

0 votes
Answer accepted
Roberts Čāčus - eazyBI
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 21, 2022

Hi @Kristin Lyons ,

The option I recommend is using the "By Status" hierarchy in the Sprint dimension. You can select the Sprint dimension simultaneously in the report rows and pages to see the future Sprints from a specific Board. See the screenshot below:

Screenshot 2022-01-21 at 12.00.34.png

If you have more than one future Sprint in the board, they will show up as well. See the result below:

Screenshot 2022-01-21 at 12.02.47.png

See more details on Sprint dimension on the eazyBI documentation page - https://docs.eazybi.com/eazybi/data-import/data-from-jira/jira-software-custom-fields#JiraSoftwarecustomfields-JiraSoftwarecustomfieldsimport.

Best,

Roberts // support@eazybi.com