how can I auto change the status of a story when it has gone past the due date?

Lisa Hartvigson
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
June 3, 2022

when a story has gone past the due date is there a way to have it auto move to a past due status and notify the owner?

1 answer

2 votes
Mohamed Benziane
Community Champion
June 3, 2022

Hi,

You could try a automation rule that will check the value of the due date (use isAfter function) and then change the status of the story.

https://confluence.atlassian.com/automation/date-and-time-functions-993924864.html