how to remove the existing sprint report without affecting the velocity report

Maralee Grajo December 24, 2022

Hi,

 

I wanna ask about something in jira scrum board velocity and sprint report, I want to remove the existing sprint but I don't want to have an issue in velocity or any reports type in jira. Is this possible to remove without any issue encountered?

check_report_de_servicing.PNG

 

Thanks and Regards,

Mara

1 answer

1 accepted

0 votes
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 25, 2022

Welcome to the Atlassian Community!

You can not.   The velocity report is entirely built upon the sprint data, so if you destroy the sprint, you can't report on velocity any more.