I am administrator of JIRA project. I have been creating sprints and completing them so long. But now when i created a new board the board says you dont have manage sprints authorization. i checked the board permissions. I am still the project lead and admin.
kindly help
Check the Project permissions. The Manage Sprint permission is set in the permission scheme for the project.
Also, if your board contains issues from multiple projects, you'll need that permission for each project.