for example (85%, etc.) because each week i need to give to my PMO the status of this sprint (% advance)
The sprint health gadgets can tell you stuff like that.
Hi Nic, but this information you said is not enough for me, i need to take The control of The status The project and i give The % advance to PMO. Could you ask to some expert in Atlassian?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I think the problem here is that you have a different definition of progress from the standard Agile one given in the gadgets. Start by defining exactly what you mean by how far through you are. What fields do you need to base the calculations on, and what are you putting in JIRA to hold that?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
As Nic says; what are you basing % advance on? Number of hours burned based on original estimate? Number of issues burned? Functional Points, etc. In order to report progress "your way", you need to ensure that you have this information in the system. So you might end up adding some custom fields to register this, and do calculations in Excel, or get someone to develop a report or similar for you.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.