jql = How to prevent epic from closing when the child tasks are not closed?

Mary Ann becker
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
June 20, 2025

jql = How to prevent epic from closing when the child tasks are not closed?

 

2 answers

1 vote
Trudy Claspill
Community Champion
June 20, 2025

Hello @Mary Ann becker 

Welcome to the Atlassian community.

Do you have access to apps that extend the capabilities of workflow customization, like ScriptRunner, JMWE, or JWT?

With only native functionality, according to Google AI you should be able to do that with a Sub-task Blocking Condition.

I don't have a Data Center environment where I can validate that is an accurate suggestion.

Screenshot 2025-06-20 at 9.09.21 AM.png

There are other methods available if you have access to third party apps that extend the workflow functionality.

0 votes
Gor Greyan
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 22, 2025

Hi @Mary Ann becker
If you are using Jira Misc Workflow Extension(JMWE) you can use the following Condition to reach your target.

Use Related Issues Status Condition, like in the screenshot.

If you don't have this add-on, please let me know, what add-ons you are using, maybe ScriptRunner?