Hi, is there an option to create a pie chart showing tasks by labels- BUT including unlabeled tasks?
Hi @Agata Puchalska ,
welcome to Atlassian Community.
1. Create a JQL for the required issues and save it with required permissions.
2. Create / Go to existing Dashboard
3. Add Gadget
4. choose pie chart
5. configure the pie chart with the above created filter.
6. Choose Static Type = Labels in configuration.
this will gives you all the information with labels and with out labels.
please try.
thanks,
kagithala babu Anvesh