Offir
Contributor
September 1, 2021

I have 2 sprints currently in my board, Sprint A, Sprint B.

Sprint A tasks are done and its finish date is already due, I would like to start Sprint B, but I can't because the `Start sprint` is disabled.

How can I enable this button and start Sprint B?

1 answer

1 accepted

3 votes
Answer accepted
Offir
Contributor
September 1, 2021

Solved by clicking the `Complete Sprint` button from Sprint A