I have an existing Kanban projecct with a Kanban board. I need to change this project to Scrum with sprints but can only create a Scrum board, but no sprints.
How can I include sprints?
Hi @JKhan , if you are using a CMP project you can create a scrum board and select the project when creating the new board. Once complete you can then chose which board you want to use via the board drop down. You should be able to create and start sprints in the backlog. If TMP project then you can turn on sprints under project settings > features.
Welcome to the Atlassian community.
Adding to this...
What is the symptom that tells you that you can't create sprints? Do you see the Create Sprint button on the Backlog screen of the Scrum board? Is it enabled or disabled?
You must have the Manage Sprints permission in the project in order to be able to create Sprints. Do you have that permission in the project?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.