Hi,

Is it possible to assign a sprint (and multiple sprints) into a version ?

Thanks

2 answers

2 accepted

1 vote
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 5, 2017

No, there's no direct relationship.

But there's nothing to stop you holding your developers to a 1:1 rule, and the system does tend nudge people toward "sprint X delivers version Y"

1 vote
Answer accepted
Thomas Schlegel
Community Champion
December 5, 2017

Hi,

no. Sprints and versions are totally independent items which can't be assigned to each other.