when ı clicked the "complete the sprint", completed issues count showing wrong

Suna Öztürk
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 7, 2023

we have already 9 issues as done status, but when ı completed the sprint, it is showing as 0, 

Screenshot 2023-08-07 at 12.49.04.pngScreenshot 2023-08-07 at 12.50.09.png

1 answer

0 votes
Marc - Devoteam
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 7, 2023

Hi @Suna Öztürk 

The configuration of your Scrum Board is incorrect.

Your last column on your board is won't, I see.

Issue in a Sprint only are "burned", based on the last column of the board (this shows as green).

So "Done" issues need to be in the last column, if the "Done" status is in another column issues are not shown as completed (burned) in the sprint.