when issue type = story moved to "Done", sub-tasks move to "Done"

sim.sisavuthary
Contributor
January 26, 2022

Dear support,

Please kindly help to guide how can I configure rule automation when we moved issue type = "Story", then sub-tasks create under that story automatically move to "Done"

1 answer

1 vote
Fabian Lim
Community Champion
January 26, 2022

Hi @sim.sisavuthary

Triggers: issue transitioned to "done"

Branch: To subtasks (https://support.atlassian.com/cloud-automation/docs/branch-automation-rules-to-perform-actions-on-related-issues/)

Action: transition to done

good luck

Fabian Lim
Community Champion
January 26, 2022

You can use this as an example: https://youtu.be/DcPYrw-Puus

but it would be the opposite of rule 1.

sim.sisavuthary
Contributor
January 26, 2022

2022-01-27_132725.png

sim.sisavuthary
Contributor
January 26, 2022

I tried with the rule in the library but it doesn't work. 

sim.sisavuthary
Contributor
January 26, 2022

thanks for your video. It works now.

Like # people like this
Fabian Lim
Community Champion
January 29, 2022

@sim.sisavuthary 

Glad that it works.  Please accept the asnwer so that people can see how to solve this issue in the future.