while copying project from Jira prod(v 7.5.2) to staging(v 7.9.1)

ashok 1234
Contributor
July 29, 2018

while copying project from Jira prod(v 7.5.2) to staging(v 7.9.1)

Getting below error:

This data appears to be from an older version of JIRA. Please upgrade the data and try again. The current version of JIRA is at build number '79001', but the supplied backup file was for build number '75007'.

TIA..

 

1 answer

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
July 29, 2018

Yes, that's correct.  The source and target systems need to be on the same version for project import to work.