why does publishing a Jira Plan change the default assignee in jira?

Steven Codd
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 27, 2024

In Plan our Epics and Story/Tasks have no assignee. Our Project default assignee is "Unassigned", yet when we publish a plan the Epic and Tasks are given an assignee,  we cant figure out where that value is coming from.

1 answer

0 votes
Tuncay Senturk _Snapbytes_
Community Champion
September 2, 2024

Hi @Steven Codd 

Welcome to the Community!

This might have several reasons, these are what I'd have a look.

  • Check for Automation Rules. There may be an automation rule in place that assigns issues automatically when they are created or something like that.
  • Check the Workflow. It’s possible that the workflow associated with the Epics and Tasks has a post function that assigns the issues upon certain transitions
  • Check default assignees of components. If the issues are being assigned based on components, check if any of the components in your project have a default assignee. 

I hope this helps