During the cloud migration process will my users still be able to access the server install of jira we currently use?
Hi John,
Using the Jira Cloud migration assistant app in Jira Server does not lock out the server instance during the migration. Because of this there is a note about such changes over in https://support.atlassian.com/migration/docs/use-the-jira-cloud-migration-assistant-to-migrate/
Changes on server before migrating
If you make any changes on your server site, wait at least 10 minutes before migrating to allow all data to be updated.
I hope this helps.
Andy