Hi! :)
While I was looking for a way to group tasks the option to Group Tasks by Duration was offered to me, a few clicks later it was gone and I don´t know how to get it back. Can someone help me?
I read that Grouping Categories have to be in a column first. But where do there technical categories come from? I didn´t put anything like that in a column but I think it would really help us to work with BigGantt.
Thank you soo much in advance!
Stella
Ok, so I think I found that those technical columns should actually not be visible to users. :(
So I think my question would rather be:
Is there a way to set a duration for a task and have that duration reflected on my issues visible in the Gantt?
Like: I set a duration of 4 weeks/20 days and also a start date to May 1. Is there a way that the End Date is calculated according to this values?
Thanks :)
The grouping option helps to display and aggregate values on a selected field value level. Moreover, you can use multilevel grouping, where the group structure will be based on the active grouping elements, and the order of grouping elements (fields) determines the group hierarchy.
Indeed, the first step to group your issues is to add a given field to the column view.
To add a new column (that you want to use as a grouping activator later on), please click on the cog icon, find a given field and simply click it to add. See my image as a reference.
Once the field is added, it will appear on the grouping activator list in Data >> Group task.
Please let me know if you have more detailed questions.
To resolve the situation you described in your post I would need more data. Could you please describe step-by-step activities preferably supported by screenshots? Thank you.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear @Anna-BigPicture
thanks for your help :)
I found the Grouping by "Duration [technical]" option and thought this would help me to set a duration for an issue and have the start or end date adjusted to that. But I think what I found was a bug and the column "Duration [technical]" should actually not be visible to users.
I can´t send any screenshots since I can´t reproduce adding the column. So now I am wondering if by any chance it is possible to have a column "Duration" (maybe as a customed jira field) and take this value to calculate the start or End Date.
Thank you :)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear @Stella Berger
You are welcome :)
Could you please provide me the information on which version of BigGantt you currently use? I’ve already reported the issue with displaying Duration [technical] to our Dev Team.
Currently, the plugin can automatically calculate the End Date based on the Original Estimate (or Time Spent + Remaining Estimate). Then the duration would be the value of the Original Estimate field (respectively Time Spent + Remaining Estimate). What you have to do is mapping the End Date to the selected field in Jira Administration >> Manage Apps >> BigGantt Technical Configuration >> General >> Tasks.
Moreover, there is a feature request in our backlog that will allow calculating End Date based on start date + duration. You can follow the functionality development works in the feature request ticket ONE-1727. Please note that it is best to open it in the incognito tab of your browser.
Please let me know if the feature described in ONE-1727 meets your expectations. I am deeply interested in your feedback :)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
yes that is the feature we would need! :D
We are working with BigGantt 8.0.20
I will try to configure what you have described above for a sample project and provide a feedback soon.
Thanks again! :)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@Stella Berger
I am waiting for your feedback then. Meanwhile if you have any questions, please let me know :)
I will gladly help :)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.