Hi,
We use BigGantt.
It is great but it doesn't take into consideration the original estimation we update.
We see some random lengths of each issue (for example we have an issue estimated 2w and it show 4 days on the gantt)
Any suggestions?
I could not find any information about it anywhere.
Thanks :)
Hi Segev,
Do you have the End Date mapped to the Original Estimate?
Let me know if that answers your question :)
Cheers,
Patryk