Hello, could you tell me if there is any way that in the creation of an Issue the components assigned to the epic or the parent associated with the new Issue created are copied?
I tried the creation and linked Issue events but it doesn't work.
Thanks in advance.
Hello,
Thank you very much. It works if the Issues are created from the epic itself but not if they are created from the User Story Map.
Is there a way that it works if the creation is done from there?
Thanks in advance.
Regards.
Hi Adriana,
yes this should be possible with a fairly simple rule:
So basically when a Story is created, this rule will edit the story and copy the components from the Epic. This rule requires though that the 'Epic link' is already established when the story is created.
Otherwise, if you are linking the Story to an epic after creation you could also use the 'Field Value Changed trigger' with the Epic link field.
Hope that helps.
Cheers,
Andreas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.