Hi there,
We are evaluating Folio to handle our EVM reporting (currently a labor intensive query/excel process). Our integrations between our current system and JIRA limit us to 1 issue per project. When we log time to a project, we also indicate a completion percent or estimate to completion. Is it possible to set Folio up in a similar way where the EVM are based on the Remaining Effort and Original Estimate for a single issue rather than the completion state of multiple issues?
Thanks,
-Rick
Community moderators have prevented the ability to post new answers.
Hi Richard,
In FOLIO 5.1 we have introduced the progressively earned value. I am pretty sure that it will nicely answer your need :)
The "progressively earned value" allows you to get credited for earned value on issues proportionally to their degree of completion. This degree of completion for an issue is computed as follow:
Degree of completion = Total Time Spent / ( Total time spent + Remaining Estiomate)
So the partial earned value of the issue is then
Partial Earned Value = Original Estimate * Degree of completion
By default, FOLIO does not use progressively earned value. This setting can be set in the folio's configuration under the "Earning Rule' section. You can set your folio to apply the progressively earned value to all issues or only on a specific set of issues based on a label set.
So in your case you would have a folio where the scope is the 1 issue of the project.
The folio would have its "progressively earned value" rule set to all issues.
Let me know if this answers your need or not :)
Cheers,
JC
Score!
This must have been a recent release, I just installed Folio last week. The Progressive Earned Value option is exactly what I needed!
Thanks,
-Rick
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The timing was actually good...
FOLIO 5.1 was released last night :)
Cheers
JC
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Richard, I would also recommend this app for seeing EVM at the issue-level:
Aneto Project Accounting System with Earned Value Management
Josh
Aneto
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can also check FOLIO's documentation for all details about Progressive Earned Value and how it is calculated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.