I am not working with Green Hopper - I am simply using Gantt to schedule my issues. Can I re-schedule an issue without manually editing the Planned Start/Planned End dates , i.e. by dragging it wihtin the chart
Yes, you can move issues left/right via drag'n drop: use left mouse button for shifting planned start date and right mouse button for shifting planned end date. If you release the mouse button, a popup allows you to specify how to treat the other end of the planning time-frame (re-calc. keeping the original number of calender days or working days or just keep the original date = modify duration instead of move issue).