I would like to create a due date for issues once they reach a certain status in my workflow.

1 answer

0 votes
David Fischer
Community Champion
September 14, 2017

Hi Chad,

you did not mention if you were already using an add-on for workflow extensions. If not, you can certainly achieve your goal using JMWE for JIRA Server or JMWE for JIRA Cloud, depending on which JIRA platform you're using. You would be using the "Set Field Value" post-function (the exact syntax depends on whether you are on Server or Cloud).

David