Here is a brief description:
I have initiatives that are divided into epics for each team's project. And then further these epics are divided into stories and tasks for team's backlog.
How can I show all three layers on big picture gantt chart?
It is possible to do using jira portfolio add-on but unfortunately, it doesn't give me a flexibility to modify gantt on the go using drag and drop functionality. Also, it is not possible to display dependencies using arrows that is provided by BP.
Any answers would be highly appreciated.
Regards,
Narender
Hi @narender mehra,
Considering that you link Epics to their corresponding Initiatives via Issue linking (in my case it is "Initiative" link), you'll need the following setup:
The above section can be found in Program configuration.
Issue linking:
Let me know if it was helpful.
Cheers.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.