How to add initiative layer in big picture?

narender mehra January 17, 2019

Here is a brief description:

I have initiatives that are divided into epics for each team's project. And then further these epics are divided into stories and tasks for team's backlog.

How can I show all three layers on big picture gantt chart?

It is possible to do using jira portfolio add-on but unfortunately, it doesn't give me a flexibility to modify gantt on the go using drag and drop functionality. Also, it is not possible to display dependencies using arrows that is provided by BP.

Any answers would be highly appreciated.

Regards,

Narender

1 answer

1 vote
Tomek-SoftwarePlant
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 22, 2019

Hi @narender mehra

Considering that you link Epics to their corresponding Initiatives via Issue linking (in my case it is "Initiative" link), you'll need the following setup:  

synchronization-part1.jpg

synchronization-part2.jpg

The above section can be found in Program configuration. 

Issue linking:

links.jpg

Let me know if it was helpful.

Cheers.