Is there a way to add estimated/planned hours at the project (not the issue) level in Tempo without doing it for every day for every person. Say Project X is going to take an estimated 480 Hours. Can I put that at the project level in Tempo?
Hi James,
The time estimation is a JIRA feature and can only be done on Issue level. In Tempo Timesheets, you can plan time on Projects, Issues and Activities (Versions and Components) but these plans are always made for a User.
In Tempo Planner you can plan time on Team level. This plan will reflect on every user in the Team. Please take a look at https://tempoplugin.jira.com/wiki/display/PLANNER022/Planner+Timeline for more information.
Kind regards,
Susanne
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.