Hi everyone!
I'm trying to create a chart that shows all the issues in a specific project, but all those issues have dependencies (blocks, or split type) on other projects.
The chart only shows me the task that are on the father project, and not the inter-project dependencies.
Does anyone know if its possible to show the dependencies in tha Gantt chart?
Any help would be apprecriated.
Thanks!
Layout > Row height > must be set to "Wide" to see the 2 dots on the side of the task bar...
Hi there,
We show cross-project dependencies in the form as on the screenshot below, this dependence must be mapped in Link configuration.
Kind regards,
Tomasz - SoftwarePlant Support
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.