For vertical lines on the Gantt:
On the Gantt portion of the Program (so NOT on the WBS side) click on the date on the timeline and a Marker dialog box will open. Make sure you have View-->Show Markers turned on. Bad thing is that they are only visible to you. If you have other users of the same program they won't see the markers you've created. kind of a bummer.
for Milestone tasks:
click on the WBS task, click on the ellipse, change Task Type to milestone (everyone sees those)
Hi Ericka,
I was able to create markers as per your instructions. So thank you for that.
Quick note, the markers I created were visible to others viewing the program. They just had to enable the show markers in their respective view settings. I don't know if that's an update since your comment but thought I'd share that.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
ah that is good news, thanks for the followup !!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.