Hello,
I'm new with JIRA tools, especially with the Big Picture Entreprise plug-in. I'm pretty entousiast in front of all possibilities nevertheless I don't know how to change the load off one issue.
For exemple, this is my ressource view :
This worker have two task on the same day so he is loaded at 16h / day. But that's not the reality. How can I configure each issue to take only 1h / day for exemple ?
Thanks in advance for your time,
Best regards,
Hello Thomas,
Thank you for your query.
At the moment BigPicture's Resource module allows user to set and to distribute a workload per resource / per day, though as we understand growing needs of our clients, we would like to add a feature which would also allow us to distribute such a workload per task / per resource / per day. This functionality is not yet available though, we are planning to implement it by the end of this year.
https://softwareplant.com/jira/browse/PPM-9
Kind Regards,
Piotr of SP Support
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.