Effect of Biggantt task movement with dependencies on the boards

Uri Shani
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 22, 2020

I’m trying to understand the functionality around moving tasks.

Let’s say my Gantt has 2 tasks that are linked.

Task A – Belongs to team X

Task B – Belongs to team Y

B can’t start before A (and the dependency was set)

 

The Scenario: A has a delay

If X team leader delays the task in Jira (via board and / or via Gantt), what happens to Task B?

  • Moves accordingly both in Gantt and in Y team leader board (meaning team leader X basically changes Y’s plan)
  • Moved only in Gantt? If yes, how does the PM or the Y team leader know B needs to move?
  • Other?

 

yes, i, very new to Jira and Biggantt :)

1 answer

0 votes
Mateusz Sołowianiuk
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 14, 2020

Hi @Uri Shani 

Please note that there are multiple factors that may influence the tool's behavior in this scenario (task modes, ASAP mode in the link, etc.), hence, it is impossible to provide a universal answer to this. 

In order to make it clearer, I encourage you to get acquainted with the wiki page related to Task Dependencies. It covers all factors that impact the influence of one task on another. 

I rest at your disposal if you have any further questions regarding this. 

Best regards,

Mateusz Sołowianiuk

SoftwarePlant Support

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
TAGS
AUG Leaders

Atlassian Community Events