Gantt chart plugin, tasks not being added automatically

Gus Oh September 30, 2013

We are evaluating the demo version of the Gantt Chart plugin. When I create a new task, it does not get added to the chart automatically. I have to force it by going to the admin section and cliekcing on the "regenerating the planning dates" button. Re-scheduling is enabled for this project. Is there any way to have the charts updated automatically when new tasks are added?

3 answers

1 accepted

0 votes
Answer accepted
Gus Oh October 6, 2013

After talking with the developer, I realized that you have to add the Planned Start and End date fields to the Create/Edit Issue screen and then fill those out for each issue. After that, the issues are added automatically to the chart.

0 votes
Frank Polscheit
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 30, 2013

Does it work properly within your envrionment after full/complete configuration?

0 votes
Frank Polscheit
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 30, 2013

Hi Gus,

not knowing anything about your environement, I assume you have installed JIRA Agile - formerly named Greenhopper - and not enabled individual planning of issues: please click on the "config" button on the top right of the Gantt-Chart, select tab "Greenhopper" and enable the following option

Sprint dates: (X) use individual issues planning dates instead of sprint start/end date.

Otherwise, you can contact me per email at frank@polscheit.de and provide me with additional information about your infrastructure and local configurations.

Regards,
Frank

Gus Oh September 30, 2013

Sorry, we have not installed Agile. But I did notice this message in the log file afterwards:

2013-10-01 14:49:56,293 http-bio-8080-exec-14 WARN goh 889x4354x1 mz8bhs 192.168.0.205 /browse/TPONE [jira.plugins.tabpanels.GanttVMparams] You have not configured an issue link type to be used as Gantt-Dependency: missing Gantt: start-start