Hello, I just downloaded WBS Gantt-Chart(9.8.0.17)-Jira and cannot add a task.
The Add button is greyed out.
I don't understand what I'm doing wrong as I have used various Gantt charts before.
Maybe I need to add tasks via Jira, which are then imported to the Gantt chart...but how?
Hi,
You probably need to confirm Jira issue permission, the user must have the
Issue creation permission in Jira to add a task to Gantt-chart. And also if you have configured to "Specified issue type" mode, you can not add it from a Project or a Version unless root setting is checked.
If you still facing the problem, please let us know and we'll be happy to look into it.
Best,
Jennifer
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.