Hello,
How do I define 'Critical Path' issue in Gantt- Chart for jira plugin
Thanks
Naama
The Gantt-Chart add-on takes the issue having the latest planned end date and all issues being a timely parent of that: all together build the critical path as a shift of at least one planned end date will result in a shift of the final end date.