I want all my linked tasks to auto calculate the dates.
In the manually scheduled column, I see most tasks with Blank and some with No. What does this mean?
Also my dates do not automatically recalculate when a new link is added until the predecessor task date is changed (even reloading doesn't update).
Hi,
If you have No on the Manually mode column it means that task isn't manually scheduled, and a project row displays in Blank. If you want to stop Auto-correct schedule running, you need to enable the setting by clicking the editing icon and check the box and make it manually mode column to Yes.
Date recalculation is not triggered until the predecessor date is manually changed in Gantt screen is actually this plugins current specification. I hope it will improve in the future.
If anyone interested in that feature, please vote for it from below link:
Best,
Jennifer
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.