How to use/control the WBS Gantt the Manually scheduled setting?

Gary Fitzgerald October 18, 2018

I want all my linked tasks to auto calculate the dates.

In the manually scheduled column, I see most tasks with Blank and some with No. What does this mean?

Also my dates do not automatically recalculate when a new link is added until the predecessor task date is changed (even reloading doesn't update). 

1 answer

0 votes
Jenny
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 9, 2018

Hi,

 If you have No on the Manually mode column it means that task isn't manually scheduled, and a project row displays in Blank. If you want to stop Auto-correct schedule running, you need to enable the setting by clicking the editing icon and check the box and make it manually mode column to Yes. 
Date recalculation is not triggered until the predecessor date is manually changed in Gantt screen is actually this plugins current specification. I hope it will improve in the future.

 If anyone interested in that feature, please vote for it from below link:

Ability to reflecting dependency of Gantt-Chart bar when users entering data in Issue Detail View of Jira

 

Best,

Jennifer