I am evaluating the Gantt-Chart and I have a question;
How do you have to configure to see the issues, for example in red, that were completed later than planned end date in Gantt Chart? So that for example in the end you could see directly from Gantt how many issues were completed late?
I tried logging in work later than planned end date, but I could not get it to show in Gantt in any special way.
What you can do is using base-lining together with my free JIRA-addon "traffic-light": in that case, the traffic-light customfield will be set to red if end date differs from baseline-end more than 20%, yellow in case of > 10% else green.
Regards,
Frank