Percent complete for Parent Issues when child task marked done.

Angie Affolter
Contributor
September 4, 2019

There is functionality available to sent the percent complete to 100 when a task is marked done.  HOWEVER, it does not go back and recalculate percent complete of the tasks above it in the hierachy.

You can go back into the Gantt and force updates, but you'd have to know which tasks were updated to know which to trigger an update.

How have folks handled this?

1 answer

0 votes
yuki
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 8, 2019

Hi,

Now, the only way to know the updating is that editing other %done(progress) fields. it makes Gantt screen (Java Script) calculates the %done(progress).
Ricksoft public tracker has the ticket below.

Thanks

Suggest an answer