How do I get the sprints to display on top of the timeline in the gantt?

Martin Härri
Contributor
April 26, 2023

I have built a structure from a project which has sprints, but these sprints are not displayed on top of the timeline above the months, quarters, or whatever time unit I am using.

I am sure I am missing a setting here, which might it be?

1 answer

0 votes
David Niro
Atlassian Partner
May 1, 2023

Hi @Martin Härri ,

If you're visualizing Months, Quarters, is it safe to assume that you are also using Structure.Gantt in addition to Structure?

If I have it right, you can find the option in the Gantt Chart Settings under Sprints.

Please let me know if this helps!

Best,
David

Martin Härri
Contributor
May 26, 2023

Hi David

Thanks for your help but I'm afraid that did not work. Here are my settings

Gantt Settings.jpg

 

And here's what I see

Gantt Look.jpg

 

So the versions are there, but not the sprints. The Scrum Board I am referring to has 3 sprints, one of them currently active, and I would assume that these would be visible as blocks on top of the timeline.

So I guess I am still missing something in the settings :-(

David Niro
Atlassian Partner
May 30, 2023

Hello @Martin Härri ,

Sorry, I seem to have pointed you to the wrong place.  You will want to Group by Sprint in your Structure and you will also want to enable the Use Sprints for Manual Scheduling option.

Once this is done, selecting one of the issues should show the sprints across the top of the timeline.

Please let me know if this helps!

Best,
David

Martin Härri
Contributor
June 23, 2023

Thank you, David. That works indeed, but unfortunately I have issues from a different Jira project under the issues from the project with the sprint. If I only have issues from the "main" structure in the Gantt then all is fine, the sprints are displayed as soon as I click on an issue. However, when I extend the structure with the issues from the other project (sub-issue delivers issue) then the sprints are not displayed anymore.

I think I give up on that topic and leave it as it is. Thanks anyway for your help!