Sync Gantt Start and Finish Dates with Start and Finish on issue

Kirk, Becky November 25, 2019

Can the Gantt Start and Finish date fields sync with the Start and Finish date fields on an issue? Our dates are getting out of sync and we cannot edit the Start and Finish Date fields that we pull from the issue into the Gantt. Is there a way to unlock those fields or a work around?

1 answer

1 vote
Hanna November 26, 2019

Dear Kirk,

> Can the Gantt Start and Finish date fields sync with the Start and Finish date fields on an issue?


Yes, you can set your custom fields as the Gantt Start and Finish date on Issue view setting( Config icon > Gantt Configuration > Issue view).

RS_WBS_1.pngRS_WBS_2.png

> Our dates are getting out of sync and we cannot edit the Start and Finish Date fields that we pull from the issue into the Gantt. Is there a way to unlock those fields or a work around?


Have you able "Non-editable" of Start/Finish date of Issue view configuration?
If you uncheck the option or have issue update permission, you might edit the fields.

Regards,
Hanayo,

Dennis Kang
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 6, 2020

Hi Hanayo,

 

I'm trying to set the start date to "start", but I am not seeing the "Issue View" 

 

I only see this: Screen Shot 2020-01-06 at 4.23.02 PM.png

Do I have to be an admin to adjust this?

sulli February 6, 2020

Hi, I have the same problem. I'm definitely the admin though. I just don't see what Hanayo sees on that screen :(

Hanna September 27, 2020

Dear Denis, sulli,

According to your screenshot of Ticket configuration, you use WBS Gantt-Chart for Jira Cloud.
As for Cloud, WBS Gantt-Chart doesn't have Start and Finish Date fields mapping function. (This feature is implemented in WBS Gantt-Chart for Jira Server and DC only.)
You can track the future request by the following suggestion ticket of their public tracker.
It would be better to watch or vote the ticket.
https://ricksoft-support.atlassian.net/browse/WGCCPT-35