Why is "Cannot start until linked issue finishes" not calculating the successor date correctly?

Gary Fitzgerald October 16, 2018

Sometimes it works after the predecessor date changes but not always. 

Also have tried other link types with similar results.

I am using the links to control when an issue starts based on it's predecessors (like in MS Project).

This is an important part of our evaluation.

Any suggestions?

1 answer

0 votes
Jenny
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 9, 2018

Hi,

I just want to let the community know that I found the request in Publick Tracker.

Ability to reflecting dependency of Gantt-Chart bar when users entering data in Issue Detail View of Jira

If anyone interested in that feature, please vote for it.

Best,

Jennifer