we installed a trial version of bigpicture and have couple of basic questions.
1) in my advanced fields i couldn't find "links" tab to be as my column. how can i modify this?
image2016-3-9 11:39:44.png
2) resource allocation. how can i set "user A" to work on issue "#2" 4 hours and "user A" to work on issue "#3" 2 hours for the specific day.
Thanks
Hi,
Just as an exmaple, a task starting on the 1st, ending on the 11th has 10 days of duration. With 100 hours of original estimate, it will be 10 hours of work each day.
Thanks Matthew,
and another question if you can please.
Can I automatically set Start Date when Issue Status is changed to "In Progress" ?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Currently not, ie status does not affect the start date. However, if you add an issue without its start date specified, it will take the position of the create's date, and issues in different statuses are color-coded.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.