Hello is it possible (if so how) to have Big picture set an issues start end date to the start end date of the iteration the issue is placed in on the BP "board" ?
Hi @luka montin
Yes, this is possible by using Task Period Alignment. Please see this wiki page for an extensive explanation of this functionality in BigPicture.
I hope that this helps. Nonetheless, I rest at your disposal if any further questions arise.
Best regards,
Mateusz Sołowianiukk
SoftwarePlant Support