Hello. In my Structure Gantt, I would like the duration of my tasks to always reflect the 'Remaining' estimate from Time Tracking.
I have a task with Original Estimate of 10 days, and I entered a time log of 3 days on it.
However, in Structure Gantt, it still shows that the task will take 10 days. I want it to show 7 days. Similarly, if I edit the Remaining Estimate field, I would want the duration to reflect the new value.
In the Gantt, the task does show that progress is 30%, but the end date is still 10 days from today.
My settings are:
Work Estimates: Use Time Tracking
Progress Calculation: Based on Work Estimates
Manual Scheduling is off
Could I please get some guidance on what values to set for this scenario?
Thank you.
Hi Claudine,
When the time is being logged, remaining estimate is adjusted in different ways. With automated adjustment you would have 3 days logged work and 7 days remaining estimate. The duration in this case is still 10 days, as it is calculated as a sum of logged work and remaining estimate. When time tracking is used for work estimates, then the duration is based either on original estimate or on sum of work logged and remaining estimate.
You mention that you edit Remaining Estimate, but the task's duration is unchanged. That is incorrect behavior, and we will need to investigate it to find out the source. Would you be able to send us at support@almworks.com a step by step scenario of how you change your remaining estimate and perhaps a couple of screenshots of how chart reflects these changes?
Sorry for the inconvenience.
Regards,
Egor Tasa
ALM Works
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.