In my Jira projects, each issue have 3 date fields ("START", "RELEASE", "DUE").
When I use Plugin Tempo I would set, in the Plan Time, the 2 field "DATE" and "END DATE" of a Period, with the "START" and "RELEASE" value.
Is it possible?
Regars
Marco
Allright, I understand what you say.
But my problem in in the "connection" between Jira issue and the Plugin tempo...
When I create an issue, I set Start Date, End Date e Due Date. I would like that those value of Start Date and End Date, could be draw on the plugin Tempo in the timesheet like Plan Time.
It is possible?
Regards
Marco
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Marco,
No, this is currently not possible, but I can see the potential benefit. Please create a feature request in our issuetracker: https://studio.plugins.atlassian.com/browse/JTMPO
Other users with similar requests can vote on these issues.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Marco, not quite sure I understand.
As the planning works today, you plan for x hours each day for the entire period of the plan. So if your end date is two weeks after the start date, and you select 8 hours per day, you are in effect planning 2*5*8 = 80 hours for those two weeks.
(We are rethinking the planning feature in upcoming Tempo products, which will increase the planning flexibility.)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.