It seems like there are 2 kinds of URLs to render WBS Gantt-Charts.
URL-1 https://<host>/secure/WBSGanttMain.jspa?filter=BOARD_89
and:
URL-2 https://<host>/secure/WBSGanttMain.jspa?filter=22719
I get URL-1 when I create a Gantt-Chart from filter 22719 (the same filter used in URL-2).
The behavior of the Gantt-Charts is different though.
URL-1 behaves as if the WBS-Gantt fields for issues are not shared with other Gantt-Charts that reference the same issues i.e. changes made in one Gantt-Chart are not seen in other Gantt-Charts.
URL-2 behaves such that the fields are shared i.e. changes made in one Gantt-Chart are seen in other Gantt-Charts.
Questions
What is going on here?
What is the difference when the WBS Gantt-Chart is rendered via the 2 URLs?
Additionally
We have WBS Gantt-Charts based on BOARDS that reference the same JIRA issues. Some of these BOARDS behave as if the WBS-Gantt fields for these issues are shared. And other BOARDS behave as if the fields are not shared.
What causes this difference in behavior for sharing of WBS-Gantt fields?
Hi,
Those two Gantt-chart has the different configuration.
URL-1 shows `Gantt` which you have created from WBS Gantt chart creating screens which reflect each own Gantt configuration. Gantt settings
The other one is 'Filter Gantt-chart' (URL-2), it reflects Global configuration (know as 'Feature settings' at 9.8.0 version or later), only administrators or system administrator have permission to configure them. (JIRA ADMINISTRATION menu> Add-ons>Feature settings)Feature settings
Best,
Jennifer
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.