I am using Jira Cloud with WBS Gantt-Chart plugin. I have a subtask with fix version = R1.1 (see diagram below: "Jira issue details"). In the gantt chart view, the subtask is correctly showing up intended under the parent task. However, I was expecting it to also show up under the R1.1 group in greyed-out/read-only manner, but it is not doing that (see diagram "gantt view" below).
Can someone please tell me how I can configure WBS Gantt-Chart to so show this? My gantt versions setting is shown below in diagram "gantt version setting".
--------------- Jira issue details --------------
------------ Gantt view --------------
```````````````` Gantt versions settings ``````````````````````````
Hello, @Lawrence Lam
Thank you for bringing this behavior to our attention and creating this Community Question. We have responded to the ticket that you have created on our Support Platform. Can you please verify it?
We are looking forward to hearing more from you on the ticket. If you need assistance with our plugins or have any other questions, please contact us anytime at Ricksoft-support.atlassian.net. I will be happy to help.
We wish you a great day!
Kind Regards,
Gabriel Quadros
Ricksoft Support Team
Thank you for responding to my post so quickly. Yes, I can see you have open a feature request WGCCPT-98 for this item.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Did you provide a fix for this issue? I am experiencing the same thing on my Gantt view.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello, @Carl Wicklund
Thank you for reaching out to us via this Community Question.
The suggested solution is still under evaluation on the WBS Gantt-Chart Product Board Portal to our development team to implement it at a code level:
We understand that not having a workaround for this behavior is not optimal, but let's give our developers some time to investigate and implement this suggestion if possible.
We are looking forward to hearing your thoughts on this matter. If you need assistance with the WBS Gantt-Chart or have any other questions, please let me know as well. I will be happy to help.
We wish you a great day!
Kind Regards,
Gabriel Quadros | Support Engineer
Ricksoft Support Team
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.