I have 4 lists: today, tomorrow, a week, more than a week.
If you create a card with a completion date, then it will move to a specific list according to the Butler rules. But then they don't automatically move through the lists. Tell me is it possible to implement it?
Hi!
Yes, you can use Butler to create due date rules which can be triggered based on when a due date is set on a card. In order for a card to trigger the rules, it will need to have a due date set that meets the criteria of the Butler rules. You can take a look at how to create due date rules in Butler here: https://help.trello.com/article/1318-creating-and-managing-butler-commands#Due-Date-commands
Thanks!
Ryan