I have a board with an In Progress list and a Completed list. Team members move completed cards to the completed list. However, sometimes people will move them over without completing all the checklist items. I want to have a rule that will move the card back to In Progress if they do this. Is this possible?
Hi @Enrique Pasos !
What a great idea. Yes, you can do this! Here's the setup you'll want:
1. When a card with an incomplete checklist is added to list Completed
2. Move the card to the top (or bottom, your preference) of the list In Progress
Screenshots:
If you wanted, you could even make a comment tagging the person who moved it to let them know they "done goofed" ;) To do that:
Well... maybe the comment should be more professional. Ha! But you get the idea.
Hope this helps!
Holy smokes @Devon Henderson !
This is perfect!!! Thx!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.