I have a business subscription to Trello and to Planyway. When I add a date to a Trello card, it shows up in Planyway because the power-up is turned on, and it shows up in Google Calendar because the integration is turned on. But when I do the same with a task entry -- add a date, it only shows up in Planyway. It doesn't show up on Google Calendar.
Anyone have an idea why that would be? I can't seem to find any selections I made that would lead to this outcome.
Thanks
Hello :)
Kindly note that only the main cards can sync to your Google calendar. Time entries that you add to cards in the time tracking mode or check items wouldn't sync, I'm afraid. This is the functionality that we'll be upgrading a bit later this year.
If you have other questions or suggestions, please feel free to reach out to us at support@planyway.com
Warm regards,
Tania
Customer support manager
planyway.com
Hi there,
Thanks for reaching out!
As Planyway is monitored by a third party, we recommend reaching out to their team for support. You can reach out to them at: support@planyway.com
You can also find out more information on how to sync the two apps here: https://planyway.com/help/#31000136206
I hope that helps!
All the best,
Lara
The Trello Team
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.