Rescheduling a persistent task

Gene Monterastelli
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 27, 2018

Is it possible to check a task complete and then have it reschedule for a future.

For example, I do something every Monday, after checking it done it now shows up for the next Monday as either a new card or the same card on a new date

1 answer

2 votes
Daniel Eads
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
August 27, 2018

Hey Gene,

Sounds like you're looking for the Card Repeater powerup. After installing the powerup, you can open a card and use the Repeat function in the Power-Ups area. It lets you select how often you want the card to come back, and at what position on which list.

Card_Repeater_2

Cheers,
Daniel

Gene Monterastelli
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 28, 2018

Thanks Daniel! Perfect...and it looks way simpler than Butler 